Revision History
E |
Updated Table 4.1, Section 6.2.1, 6.4.1, 6.4.4, 7.2.1, 7.5.3 and Appendix K |
28 May 2019 |
D |
Revision based on AFCDs comments |
13 March 2019 |
C |
Revision based on AFCD and EPDs comments |
17 January 2019 |
B |
Revision on Section 11 |
24 December 2018 |
A |
First Submission |
14 December 2018 |
Rev. |
Description of Modification |
Date |
Content
2. Marine Water Quality Monitoring
8. Summary of Monitoring Exceedance, Complaints, Notification of Summons and Prosecutions
11. Conclusion and Recommendations
Appendix A |
|
Appendix B |
Summary of Implementation Status of Environmental Mitigation |
Appendix C |
|
Appendix D |
|
Appendix E |
|
Appendix F |
|
Appendix G |
|
Appendix H |
|
Appendix I |
|
Appendix J |
|
Appendix K |
|
Appendix L |
|
Appendix M |
|
Appendix N |
|
Appendix O |
|
Appendix P |
Executive Summary
Introduction
A1. The Project, Integrated Waste Management Facility (IWMF), is a Designated Project under the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO) and is currently governed by a Further Environmental Permit (FEP No. FEP-01/429/2012/A) for the construction and operation of the Project.
A2. In accordance with the Updated Environmental Monitoring and Audit (EM&A) Manual for the Project, EM&A works for marine water quality, noise, waste management and ecology should be carried out by Environmental Team (ET), Acuity Sustainability Consulting Limited (ASCL), during the construction phase of the Project.
A3. This is the 5th Monthly EM&A Report, prepared by ASCL, for the Project summarizing the monitoring results and audit findings of the EM&A programme at and around Shek Kwu Chau (SKC) during the reporting period from 1 November 2018 to 30 November 2018.
Summary of Main Works Undertaken & Key Mitigation Measures Implemented
A4. Key activities carried out in this reporting period for the Project included the following:
· Marine Site Investigation Works
· Coring of DCM samples conducted at site trial location
· Laying of Geotextile and Sand Blanket
A5. The major environmental impacts brought by the above construction activities include:
· Water quality impact from DCM installation and laying of sand blanket
· Disturbance and possible trapping of Finless Porpoise by silt curtains
A6. The key environmental mitigation measures implemented for the Project in this reporting period associated with the construction activities include:
· Reduction of noise from equipment and machinery on-site;
· Installation of silt curtains for DCM installation and sand blanket laying works;
· Sorting and storage of general refuse and construction waste;
· Management of chemicals and avoidance of oil spillage on-site; and
· Implementation of MMEZ (Marine Mammal Exclusion Zone) and inspection of enclosed environment within silt curtains as per DMPFP (Detailed Monitoring Programme of Finless Porpoise)
Summary of Exceedance & Investigation & Follow-up
A7. The EM&A works for construction noise, water quality, construction waste, coral, marine mammal and White-Bellied Sea Eagle (WBSE) were conducted during the reporting period in accordance with the Updated EM&A Manual.
A8. No exceedance of the Action or Limit Levels in relation to the construction noise, construction waste, coral and WBSE monitoring was recorded in the reporting month.
A9. Forty-eight of the water quality monitoring results for Suspended Solid (SS) obtained during the reporting period had exceeded the relevant Action or Limit Levels, where findings from investigations carried out immediately for each of the exceedance cases had showed that these exceedances were unrelated to the Project.
A10. No project-related Action Level & Limit Level exceedance was recorded.
A11. Weekly site inspections of the construction works by ET were carried out on 6, 13, 20 and 27 November to audit the mitigation measures implementation status. Monthly joint site inspection was carried out on 20 November 2018 by ET and IEC. Observations have been recorded in the site inspection checklists and provided to the contractors together with the appropriate follow-up actions where necessary.
Complaint Handling and Prosecution
A12. No project-related environmental complaint was received during the reporting period.
A13. Neither notifications of summons nor prosecution was received for the Project.
Reporting Change
A14. There were no changes to be reported that may affect the on-going EM&A programme.
Summary of Upcoming Key Issues and Key Mitigation Measures
A15. Key activities anticipated in the next reporting period for the Project will include the following:
· Marine Site Investigation Works
· Coring of DCM samples conducted at site trial location
· Coring of DCM samples conducted at DCM Static Lading Test sites
· Coring for Instrumentation at DCM Static Lading Test sites
· Laying of Geotextile and Sand Blanket for DCM Injection Works
A16. The major environmental impacts brought by the above construction activities will include:
· Water quality impact from laying of sand blanket
· Disturbance and possible trapping of Finless Porpoise by silt curtains
A17. The key environmental mitigation measures for the Project in the coming reporting period associated with the construction activities will include:
· Reduction of noise from equipment and machinery on-site;
· Installation of silt curtains for the sand blanket laying works;
· Sorting, recycling, storage and disposal of general refuse and construction waste;
· Management of chemicals and avoidance of oil spillage on-site, especially under heavy rains and adverse weather; and
· Implementation of MMEZ and inspection of enclosed environment within silt curtains as per DMPFP
· Ground Treatment works;
· Seawall and Breakwater construction;
· Non-dredged Reclamation;
· Other Marine works and Harbour and Port Facilities,
· Site formation,
· Municipal Solid Waste (MSW) Treatment Processes,
· Energy Recovery for Power Generation and Surplus Electricity export,
· Wastewater treatment process,
· Desalination and water treatment process,
· Civil works;
· Building and Structural works,
· Electrical and Mechanical works,
· Building Services,
· Architectural and Landscaping works, and
· All other design and works required for the operation and maintenance of the Facility
· according to the Contract requirements
1.1.4 The location of the IWMF near Shek Kwu Chau (SKC) and general layout of IWMF are shown in Figure 1.1 and Figure 1.2 respectively.
|
Figure 1.1 Location of the IWMF at the Artificial Island near SKC |
|
Figure 1.2 General Layout of the IWMF at the Artificial Island near SKC |
1.3.2 |
Figure 1.3 Project Organization Chart |
Table 1.1 Contact Details of Key Personnel
Party |
Position |
Name |
Telephone no. |
Keppel Seghers Zhen Hua Joint Venture |
Project Manager |
Kenny Yu |
2192-0606 |
Acuity Sustainability Consulting Limited |
Environmental Team Leader |
Gabriel Lam |
2698-6833 |
ERM-Hong Kong, Limited |
Independent Environmental Checker |
Mandy To |
2271-3000 |
Table 1.2 Summary of the Construction Activities Undertaken during the Reporting Month
Location of works |
Construction activities undertaken |
Remarks on progress |
Seawall and breakwater locations |
· Marine site investigation works |
· 51 out of 56 drill holes were completed |
Location of DCM Site Trial |
· Coring of DCM samples |
· Completed |
Seawall locations |
· Collecting of Marine Sediment Samples |
· Completed |
Location of DCM Static Loading Test |
· DCM installation |
· Completed |
Seawall and breakwater locations |
· Laying of Geotextile and Sand Blanket |
· 42 out of 48 geotextiles were laid · On-going for sand blanket laying |
Table 1.3 Summary of the Status of Valid Environmental Licence, Notification, Permit and Documentations
Permit/ Licences/ Notification |
Reference |
Validity Period |
Remarks |
Variation of Environmental Permit |
EP-429/2012/A |
Throughout the Contract |
|
Further Environmental Permit |
FEP-01/429/2012/A |
Throughout the Contract |
|
Notification of Construction Works under the Air Pollution Control (Construction Dust) Regulation (Form NA) |
Ref No.: 428778 |
15/12/2017-22/09/2024 |
|
Wastewater Discharge Licence |
- |
- |
Under Application |
- |
- |
Under Application |
|
Chemical Waste Producer Registration |
WPN0017-933-K3301-01 |
Throughout the Contract |
|
WPN5213-961-K3301-02 |
Throughout the Contract |
|
|
Construction Noise Permit |
GW-RS0534-18 |
22/6/2018-20/12/2018 |
|
Billing Account for Disposal of Construction Waste |
A/C No.:7029768 |
Throughout the Contract |
|
Table 1.4 Summary of Status for Key Environmental Aspects under the Updated EM&A Manual
1.5.3 Other than the EM&A works by ET, environmental briefings, trainings and regular environmental management meetings were conducted, in order to enhance environmental awareness and closely monitor the environmental performance of the contractors. 1.5.4 The EM&A programme has been implemented in accordance with the recommendations presented in the approved EIA Report and the Updated EM&A Manual. A summary of implementation status of the environmental mitigation measures for the construction phase of the Project during the reporting period is provided in Appendix B.Table 2.1 Water Quality Monitoring Parameters, Frequency and Duration
Parameter, unit |
Frequency |
No. of Depths |
· Water Depth(m) · Temperature(oC) · Salinity(ppt) · pH (pH unit) · Dissolved Oxygen (DO)(mg/L and % of saturation) · Turbidity(NTU) · Suspended Solids (SS), mg/L · Total alkalinity · Current velocity · Direction |
Impact monitoring: 3 days per week, at mid-flood and mid-ebb tides
|
3 water depths: 1m below sea surface, mid-depth and 1m above sea bed. If the water depth is less than 3m, mid-depth sampling only. If water depth less than 6m, mid-depth may be omitted.
|
|
Figure 2.1 Water monitoring locations at Artificial Island near SKC |
Table 2.2 - Locations of Marine Water Quality Stations
Monitoring station |
Description |
Easting |
Northing |
B1 |
Beach - Cheung Sha Lower |
813342 |
810316 |
B2 |
Beach - Pui O |
815340 |
811025 |
B3 |
Beach - Yi Long Wan |
817210 |
808395 |
B4 |
Beach - Tai Long Wan |
817784 |
808682 |
H1 |
Horseshoe Crab - Shek Kwu Chau |
816477 |
806953 |
C1 |
Control Station |
810850 |
806288 |
C2 |
Control Station |
819421 |
808053 |
F1 |
Cheung Sha Wan Fish Culture Zone |
818631 |
810966 |
S1 |
Submarine Cable Landing Site |
814245 |
810335 |
S2 |
Submarine Cable |
815076 |
807747 |
S3 |
Submarine Cable Landing Site |
816420 |
805621 |
CR1 |
Coral |
817144 |
805597 |
CR2 |
Coral |
816512 |
805882 |
M1 |
Tung Wan |
821572 |
807799 |
· Two monitoring stations upstream and at 150 m envelope of DCM group works area (Representative Control stations).
· Five monitoring stations downstream and at 150 m envelope of DCM group works area (Impact 1 stations).
· Five monitoring stations downstream and at 250 m envelope of DCM group works area (Impact 2 stations).
· Monitoring stations should be at least 50 m apart;
· Downstream monitoring stations should be perpendicular to the tidal direction.
|
Figure 2.2 Water monitoring locations during intensive DCM monitoring |
In-situ Measurement
2.4.4 Levels of DO, pH, temperature, turbidity and salinity would be measured in-situ by portable and weatherproof measuring instrument, e.g. YSI ProDSS and Horiba U-53 Multiparameter complete with cable and sensor. (Refer to http://www.ysi.com/ProDSS for YSI ProDSS technical specification and http://www.horiba.com/process-environmental/products/water-treatment-environment/details/u-50-multiparameter-water-quality-checker-368/ for Horiba U-53 technical specification ). Water current velocity and Water Current direction would be measured by portable and weatherproof current meter, e.g. SonTek Hydrosurveyor (Refer to https://www.sontek.com/media/pdfs/riversurveyor-s5-m9-brochure.pdf for SonTek Hydrosurveyor M9 technical specification). Parameters measured by in-situ measurement is tabulated in Table 2.3Table 2.3 - Parameters Measured by In-situ Measurement
Parameter |
Resolution |
Range |
Temperature |
0.1 oC |
-5-70 oC |
Dissolved Oxygen (DO) |
0.01 mg/L |
0-50.0 mg/L |
Turbidity |
0.1 NTU |
0-1000 NTU |
pH |
0.01 pH |
pH 0-14 |
Salinity |
0.01 ppt |
0-40 ppt |
Water Current Velocity |
0.001m/s |
±20m/s |
Water Current Direction |
±1o |
±2o |
Laboratory Analysis
2.4.5 Analysis of Total Alkalinity and SS should be carried out in a HOKLAS accredited laboratory, as shown in Appendix E. Sufficient water samples shall be collected at the monitoring stations for carrying out the laboratory determinations. The determination work should be started within 24 hours after collection of the water samples. Analytical methods and detection limits for SS and total alkalinity are present in Table 2.4.
Table 2.4 - Analytical Methods Applied to Water Quality Samples
Parameter |
Analytical method |
Detection Level |
Suspended Solids, SS |
APHA 2540 Di |
1 mg/L |
Total Alkalinity |
APHA 2320 |
0.01 mg/L |
i. "APHA 2540 D" stands for American Public Health Association Standard Methods for the Examination of Water and Wastewater, 23rd Edition.
Field Log
2.4.6 Other relevant data was recorded, such as: monitoring location / position, time, water depth, weather conditions and any special phenomena underway near the monitoring station. 2.5 Monitoring Equipment 2.5.1 Equipment used in the impact water quality monitoring programme is summarized in Table 2.5 below. Calibration certificates for the water quality monitoring equipment are attached in Appendix F.Table 2.5 Impact Water Quality Monitoring Equipment
Monitored Parameter |
Equipment |
Brand and Model |
DO, Temperature, Salinity, pH and Turbidity |
Multi-functional Meter |
YSI ProDSS |
Coordinates |
Positioning Equipment |
Garmin GPSMAP 78s |
Water depth |
Water Depth Detector |
Hummingbird 160 Portable |
SS |
Water Sampler |
Wildco 2 L Water Sampler with messenger |
The instrument was a portable and weatherproof DO probe mounted on the multi-functional meter complete with cable and sensor, and use a DC power source. The equipment was capable of measuring:
l A DO level in the range of 0 ‑ 50 mg/L; and
l Temperature of -5 ‑ 70 degree Celsius.
2.5.3 Turbidity Measurement InstrumentThe instrument was a portable and weatherproof turbidity-measuring probe mounted on the multi-functional meter using a DC power source. It had a photoelectric sensor capable of measuring turbidity between 0 - 1000 NTU.
2.5.4 pH Measurement InstrumentThe probe was consisted of a potentiometer, a glass electrode, a reference electrode and a temperature-compensating device mounted on the multi-functional meter. It was readable to 0.1 pH in a range of 0 to 14. Standard buffer solutions of at least pH 7 and pH 10 were used for calibration of the instrument before and after use.
2.5.5 Salinity Measurement InstrumentA portable salinometer mounted on the multi-functional meter capable of measuring salinity in the range of 0-40 parts per thousand (ppt) was provided for measuring salinity of the water at each monitoring location.
2.5.6 SamplerThe water sampler comprised a transparent PVC cylinder, with a capacity of not less than 2 litres, which can be effectively sealed with latex cups at both ends. The sampler have a positive latching system to keep it open and prevent premature closure until released by a messenger when the sampler is at the selected water depth.
2.5.7 Sample Containers and StorageWater samples for SS were stored in high density polythene bottles with no preservative added, packed in ice (cooled to 4°C without being frozen) and delivered to the laboratory and analysed as soon as possible after collection. Sufficient volume of samples was collected to achieve the detection limit stated in Table 2.4.
2.5.8 Water Depth DetectorA portable, battery-operated echo sounder was used for the determination of water depth at each designated monitoring station. This unit could either be hand held or affixed to the bottom of the work boat, if the same vessel is to be used throughout the monitoring programme.
2.5.9 Monitoring Position EquipmentHand-held digital Differential Global Positioning System (DGPS) with way point bearing indication and Radio Technical Commission for maritime (RTCM) Type 16 error message screen pop-up facilities (for real-time auto-display of error messages and DGPS corrections from the Hong Kong Hydrographic Office) was provided and used to ensure that the water sampling locations were correct during the water quality monitoring work.
2.6 Maintenance and Calibration 2.6.1 The multi-functional meters were checked and calibrated before use. Multi-functional meters were certified by a laboratory accredited under HOKLAS or any other international accreditation scheme, and subsequently re-calibrated at three monthly intervals throughout all stages of the water quality monitoring. Responses of sensors and electrodes were checked with certified standard solutions before each use. Wet bulb calibration for a DO meter was carried out before commencement of monitoring and after completion of all measurements each day. Calibration was not conducted at each monitoring location as daily calibration is adequate for the type of DO meter employed. 2.6.2 Sufficient stocks of spare parts were provided and maintained for replacements when necessary. Backup monitoring equipment was prepared for uninterrupted monitoring during equipment maintenance or calibration during monitoring. 2.7 Action and Limit Levels 2.7.1 The Action and Limit Levels have been set based on the derivation criteria specified in the Updated EM&A Manual and Detailed DCM Plan, as shown in Table 2.6 below.Table 2.6 Criteria of Action and Limit Levels for Water Quality
Parameters |
Action |
Limit |
Construction Phase Impact Monitoring |
||
DO in mg/L |
≤ 5 %-ile of baseline data |
≤ 4 |
SS in mg/L |
≥ 95 %-ile of baseline data or 120% of control stations SS at the same tide of the same day of measurement, whichever is higher |
≥ 99 %-ile of baseline data or 130% of control station's SS at the same tide of the same day of measurement, whichever is higher |
Turbidity in NTU |
≥ 95 %-ile of baseline data or 120% of control stations turbidity at the same tide of the same day of measurement, whichever is higher |
≥ 99 %-ile of baseline data or 130% of control station's turbidity at the same tide of the same day of measurement, whichever is higher |
Temperature in°C |
1.8°C above the temperature recorded at representative control station at the same tide of the same day |
2°C above the temperature recorded at representative control station at the same tide of the same day |
Total Alkalinity in mg/L |
≥ 95 %-ile of baseline data or 120% of representative control station at the same tide of the same day, whichever is higher |
≥ 99 %-ile of baseline data or 130% of representative control station at the same tide of the same day, whichever is higher |
Table 2.7 Derived Action and Limit Levels for Water Quality Monitoring (Dry Season)
Parameters |
Action |
Limit |
Construction Phase Impact Monitoring |
||
DO in mg/L |
≤ 7.13 |
≤ 4 |
SS in mg/L |
≥ 8 or 120% of control stations SS at the same tide of the same day of measurement, whichever is higher |
≥ 10 or 130% of control station's SS at the same tide of the same day of measurement, whichever is higher |
Turbidity in NTU |
≥ 5.6 or 120% of control stations turbidity at the same tide of the same day of measurement, whichever is higher |
≥ 12.8 or 130% of control station's turbidity at the same tide of the same day of measurement, whichever is higher |
Temperature in°C |
1.8°C above the temperature recorded at representative control station at the same tide of the same day |
2°C above the temperature recorded at representative control station at the same tide of the same day |
Total Alkalinity in mg/L |
≥116 or 120% of control stations Total Alkalinity at the same tide of the same day of measurement, whichever is higher |
≥ 118 or 130% of control stations Total Alkalinity at the same tide of the same day of measurement, whichever is higher |
Notes:
i. "Depth-averaged" is calculated by taking the arithmetic means of reading of all three depths.
ii. For DO, non-compliance of the water quality limits occurs when monitoring result is lower than the limits.
iii. For turbidity, SS and Salinity, non-compliance of the water quality limits occurs when monitoring result is higher than the limits.
Table 2.8 Derived Action and Limit Levels for Water Quality (Wet Season)
Parameters |
Action |
Limit |
Construction Phase Impact Monitoring |
||
DO in mg/L |
≤ 5.28 |
≤ 4 |
SS in mg/L |
≥ 12 or 120% of control stations SS at the same tide of the same day of measurement, whichever is higher |
≥ 14 or 130% of control station's SS at the same tide of the same day of measurement, whichever is higher |
Turbidity in NTU |
≥ 4.0 or 120% of control stations turbidity at the same tide of the same day of measurement, whichever is higher |
≥ 4.3 or 130% of control station's turbidity at the same tide of the same day of measurement, whichever is higher |
Temperature in°C |
1.8°C above the temperature recorded at representative control station at the same tide of the same day |
2°C above the temperature recorded at representative control station at the same tide of the same day |
Total Alkalinity in mg/L
|
≥ 116 mg/L or 120% of representative control station at the same tide of the same day, whichever is higher |
≥ 118 mg/L or 130% of representative control station at the same tide of the same day, whichever is higher
|
Notes:
i. "Depth-averaged" is calculated by taking the arithmetic means of reading of all three depths.
ii. For DO, non-compliance of the water quality limits occurs when monitoring result is lower than the limits.
iii. For turbidity, SS and Salinity, non-compliance of the water quality limits occurs when monitoring result is higher than the limits.
2.7.3 If exceedances were found during water quality monitoring, the actions in accordance with the Event and Action Plan shall be carried out according to Appendix G. 2.8 Monitoring Results and Observations 2.8.1 During the reporting period, general water quality monitoring was conducted on 1, 3, 5, 7, 9, 13, 15, 17, 19, 21, 23, 26, 28 & 30 November 2018 at all the eleven monitoring stations. No regular DCM monitoring including monitoring station S1, S2 and S3 were conducted during reporting period. Monitoring results of 7 key parameters: Salinity, DO, turbidity, SS, pH, temperature and total alkalinity in this reporting month, are summarized in Table 2.9, and details results are presented in Appendix D.
Table 2.9 Summary of Impact Water Quality Monitoring Results
Locations |
Parameters |
||||||||
Salinity (ppt) |
Dissolved Oxygen (mg/L) |
pH |
Turbidity (NTU) |
Suspended Solids (mg/L) |
Temp. (oC) |
Total Alkalinity (mg/L) note ii |
|||
Surface & Middle |
Bottom |
||||||||
B1 |
Avg. |
30.00 |
8.07 |
8.05 |
8.10 |
3.6 |
9.68 |
22.8 |
- |
Min. |
29.04 |
7.44 |
7.58 |
7.29 |
1.3 |
3.00 |
21.5 |
- |
|
Max. |
31.19 |
8.86 |
8.59 |
8.40 |
6.5 |
24.00 |
24.4 |
- |
|
B2 |
Avg. |
30.00 |
8.01 |
7.99 |
8.08 |
3.6 |
11.63 |
22.8 |
- |
Min. |
29.04 |
7.41 |
7.55 |
7.15 |
0.9 |
5.00 |
21.5 |
- |
|
Max. |
31.20 |
8.60 |
8.54 |
8.36 |
6.8 |
49.00 |
24.4 |
- |
|
B3 |
Avg. |
30.01 |
8.00 |
7.96 |
8.08 |
3.7 |
10.54 |
22.8 |
- |
Min. |
29.02 |
7.54 |
7.59 |
7.25 |
1.0 |
4.00 |
21.5 |
- |
|
Max. |
31.20 |
8.60 |
8.41 |
8.40 |
6.9 |
23.00 |
24.4 |
- |
|
B4 |
Avg. |
29.98 |
7.94 |
7.96 |
8.08 |
3.6 |
10.60 |
22.8 |
- |
Min. |
29.01 |
7.23 |
7.48 |
7.06 |
1.0 |
4.00 |
21.5 |
- |
|
Max. |
31.18 |
8.32 |
8.29 |
8.40 |
6.6 |
22.00 |
24.4 |
- |
|
C1 |
Avg. |
30.03 |
8.03 |
8.02 |
8.10 |
3.6 |
10.14 |
22.9 |
- |
Min. |
29.00 |
7.40 |
7.52 |
7.28 |
1.0 |
4.00 |
21.5 |
- |
|
Max. |
31.20 |
8.67 |
8.38 |
8.40 |
6.3 |
23.00 |
24.4 |
- |
|
C2 |
Avg. |
29.98 |
8.03 |
8.03 |
8.07 |
3.7 |
11.39 |
22.9 |
- |
Min. |
29.01 |
7.47 |
7.51 |
7.23 |
0.9 |
4.00 |
21.5 |
- |
|
Max. |
31.20 |
8.44 |
8.49 |
8.36 |
7.0 |
24.00 |
24.4 |
- |
|
CR1 |
Avg. |
30.03 |
8.01 |
8.00 |
8.08 |
3.7 |
10.77 |
22.9 |
- |
Min. |
29.03 |
7.33 |
7.36 |
7.22 |
1.1 |
4.00 |
21.5 |
- |
|
Max. |
31.20 |
8.72 |
8.51 |
8.40 |
6.0 |
26.00 |
24.4 |
- |
|
CR2 |
Avg. |
30.00 |
7.96 |
7.97 |
8.09 |
3.7 |
12.48 |
22.9 |
- |
Min. |
29.00 |
7.44 |
7.57 |
7.25 |
1.0 |
5.00 |
21.5 |
- |
|
Max. |
31.20 |
8.53 |
8.49 |
8.40 |
6.6 |
56.00 |
24.4 |
- |
|
F1 |
Avg. |
30.00 |
8.01 |
8.00 |
8.07 |
3.7 |
10.76 |
22.8 |
- |
Min. |
29.00 |
7.38 |
7.52 |
7.14 |
1.0 |
4.00 |
21.5 |
- |
|
Max. |
31.20 |
8.70 |
8.53 |
8.39 |
6.9 |
21.00 |
24.4 |
- |
|
H1 |
Avg. |
30.00 |
8.10 |
8.02 |
8.08 |
3.7 |
10.64 |
22.9 |
- |
Min. |
29.02 |
7.48 |
7.38 |
7.19 |
1.0 |
4.00 |
21.5 |
- |
|
Max. |
31.19 |
8.73 |
8.54 |
8.38 |
7.0 |
23.00 |
24.4 |
- |
|
M1 |
Avg. |
30.02 |
8.03 |
8.02 |
8.06 |
3.5 |
11.11 |
22.8 |
- |
Min. |
29.01 |
7.28 |
7.35 |
7.09 |
1.1 |
5.00 |
21.5 |
- |
|
Max. |
31.19 |
8.47 |
8.42 |
8.39 |
6.7 |
26.00 |
24.4 |
- |
|
S1
|
Avg. |
- |
- |
- |
- |
- |
- |
- |
- |
Min. |
- |
- |
- |
- |
- |
- |
- |
- |
|
Max. |
- |
- |
- |
- |
- |
- |
- |
- |
|
S2
|
Avg. |
- |
- |
- |
- |
- |
- |
- |
- |
Min. |
- |
- |
- |
- |
- |
- |
- |
- |
|
Max. |
- |
- |
- |
- |
- |
- |
- |
- |
|
S3
|
Avg. |
- |
- |
- |
- |
- |
- |
- |
- |
Min. |
- |
- |
- |
- |
- |
- |
- |
- |
|
Max. |
- |
- |
- |
- |
- |
- |
- |
- |
Notes:
i. "Avg", Min and Max is the average, minimum and maximum respectively of the data from measurements conducted under mid-flood and mid-ebb tides at three water depths, except that of DO where the data for Surface & Middle and Bottom are calculated separately.
ii. Total alkalinity test only conducted on DCM working day with referring master programme in Appendix A.
iii. Monitoring at S1, S2 and S3 shall only be conducted during DCM work period referring to master programme in Appendix A.
2.8.2 Mid-ebb water monitoring at B1, B2, B3, B4, H1, CR1, CR2, F1 & M1 and whole mid-flood water monitoring originally scheduled on 1 November 2018 were cancelled due to the issue of Typhoon Signal No.3 during the monitoring event as shown in Appendix C. 2.8.3 The weather conditions during the monitoring period were mainly sunny and cloudy. Sea conditions for the majority of monitoring days were either light or moderate. No major pollution source and extreme weather which might affect the results were observed during the impact monitoring. 2.8.4 During the impact monitoring period for November 2018, forty-eight of the water quality monitoring results for Suspended Solid (SS) obtained during the reporting period had exceeded the relevant Action or Limit Levels, where findings from investigations carried out immediately for each of the exceedance cases had showed that these exceedances were unrelated to the Project, however, environmental deficiencies of the Contractor on the implementation of silt curtain deployment system were spotted. Details of the exceedance are presented in Section 8. 2.8.5 Implemented mitigation measures minimizing the adverse impacts on water are listed in the implementation schedule given in Appendix B.Table 3.1 Noise Monitoring Parameters, Time, Frequency and Duration
Monitoring Station |
Time |
Duration |
Parameters |
M1/ N_S1, M2/ N_S2, M3/ N_S3 |
Daytime: 0700-1900 hrs (during normal weekdays, not include Sunday or general holiday) |
Once per week Leq 5min/Leq 30min (average of 6 consecutive Leq 5min) |
Leq, L10 & L90 |
|
Figure 3.1 Noise monitoring locations at SKC |
Table 3.2 Noise Monitoring Location
Station |
NSR ID in EIA Report |
Noise Monitoring Location |
Type of sensitive receiver(s) |
Measurement Type |
M1 |
N_S1 |
Shek Kwu Chau Treatment & Rehabilitation Centre Hostel 1 |
Residential |
Façade |
M2 |
N_S2 |
Shek Kwu Chau Treatment & Rehabilitation Centre Hostel 2 |
Residential |
Façade |
M3 |
N_S3 |
Shek Kwu Chau Treatment & Rehabilitation Centre Hostel 3 |
Residential |
Façade |
l The microphone head of the lead level meter was normally positioned 1m exterior of the noise sensitive façade and lowered sufficiently so that the buildings external wall acts as a reflecting surface.
l The battery condition was checked to ensure good functioning of the meter.
l Parameters such as frequency weighting, the time weighting and the measurement time were set as follows:
- Frequency weight: A
- Time weighting: Fast
- Measurement time: 5 minutes
l Prior to and after noise measurement, the meter was calibrated using the calibrator for 94.0 dB at 1000Hz. If the difference in the calibration level before and after measurement is more than 1.0 dB, the measurement was considered invalid and repeat of noise measurement was required after re-calibration or repair of the equipment.
l Noise monitoring was carried out for 30 mins by sound level meter. At the end of the monitoring period, noise levels in term of Leq, L10,and L90 were recorded. In addition, site conditions and noise sources were recorded when the equipment were checked and inspected.
l All the monitoring data within the sound level meter system was downloaded through the computer software.
3.5 Monitoring Equipment 3.5.1 Integrated sound level meter was used for the noise monitoring. The meter shall be in compliance with the International Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications. 3.5.2 Equipment used in the impact noise monitoring programme is summarized in Table 3.3 below. Calibration certificates for the noise monitoring equipment are attached in Appendix H.Table 3.3 Impact Noise Monitoring Equipment
Equipment |
Brand and Model |
Sound Level Meter |
Nti XL2 |
Sound Level Meter Calibrator |
Pulsar 105 |
l The microphone head of the sound level meter and calibrator were cleaned with a soft cloth at quarterly intervals.
l The sound level meter and calibrator were checked and calibrated at yearly intervals
l Immediately prior to and following each noise measurement the accuracy of the sound level meter shall be checked using an acoustic calibrator generating a known sound pressure level at a known frequency. Measurements may be accepted as valid only if the calibration levels from before and after the noise measurement agree to within 1.0dB.
3.7 Action and Limit Levels 3.7.1 The Action/Limit Levels in line with the criteria of Practice Note for Professional Persons (ProPECC PN 2/93) Noise from Construction Activities Non-statutory Controls and Technical Memorandum on Environmental Impact Assessment Process issued by HKSAR Environmental Protection Department [EPD] under the Environmental Impact Assessment Ordinance, Cap 499, S.16 are presented in Table 3.4.Table 3.4 Action and Limit Levels for Noise
Time Period |
Action |
Limit (dB(A)) |
0700-1900 hrs on normal weekdays |
When one documented complaint is received |
75 dB(A) |
Table 3.5 Summary of Field Observation
Monitoring Station |
Major Noise Source |
M1 |
Installation of air-conditioning units nearby |
M2 |
Installation of air-conditioning units nearby |
M3 |
Air-conditioning units nearby |
3.8.4 No data from impact monitoring has exceeded the stipulated limit level at 75 dB(A).
Table 3.6 Summary of Impact Noise Monitoring Results
Location |
Noise in dB(A) |
||
Range of Leq 30min |
Range of L10 5min |
Range of L90 5min |
|
M1 |
48.8 60.8 |
48.1 63.0 |
45.2 60.3 |
M2 |
51.9 60.6 |
51.5 66.5 |
44.6 55.3 |
M3 |
51.1 54.7 |
52.4 58.4 |
46.5 53.7 |
4. Waste 4.1 The waste generated from this Project includes inert construction and demolition (C&D) materials, and non-inert C&D materials. Non-inert C&D materials are made up of general refuse, vegetative wastes and recyclable wastes such as plastics and paper/cardboard packaging waste. Steel materials generated from the project are also grouped into non-inert C&D materials as the materials were not disposed of with other inert C&D materials. 4.2 As advised by the Contractor, 0 m3 of C&D material was generated on site in the reporting month. For C&D waste, no metals was generated and collected by registered recycling collector. No paper cardboard packing were generated on site and collected by registered recycling collector. No plastic and chemical waste was collected by registered recycling collector and licensed chemical waste collectors respectively. 0 m3 of other types of wastes (e.g. general refuse) were generated on site and disposed of at Landfill. 4.3 Chemical waste generated from the cleaning of oil stain and leakage on deck of barges was now stored in the chemical waste storage area on the barges. The Contractor has reported that the chemical waste collection is under arrangement. 4.4 With reference to relevant handling records and trip tickets of this Project, the quantities of different types of waste generated in the reporting month are summarised in Table 4.1. Details of cumulative waste management data are presented as a waste flow table in Appendix K.
Table 4.1 Quantities of Waste Generated from the Project
4.5 Although there is not much
Reporting Month |
Actual Quantities of Inert C&D Materials Generated Monthly |
Actual Quantities of C&D Wastes Generated Monthly |
||||||||||||
Total Quantity Generated |
Hard Rock and Large Broken Concrete (see Note 1) |
Reused in the Contract |
Reused in other Projects |
Disposed as Public Fill |
Imported Fill |
Metals |
Paper / cardboard packaging |
Plastics (see Note 2) |
Chemical Waste |
Others, e.g. general refuse (see Note 3) |
||||
Sand |
Public Fill |
Rock |
||||||||||||
(in ,000m3) |
(in ,000m3) |
(in ,000m3) |
(in ,000m3) |
(in ,000m3) |
(in ,000m3) |
(in ,000kg) |
(in ,000kg) |
(in ,000kg) |
(in ,000kg) |
(in ,000L) |
(in ,000m3) |
|||
November 2018 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Notes:
1. Broken concrete for recycling into aggregates.
2. Plastic refer to plastic bottles / containers, plastic sheets / foam from packaging materials.
3. Use the conversion factor: 1 full load of dumping truck being equivalent to 6.5m3 by volume.
4.6 waste generation anticipated in the coming month from the Project, the Contractor is advised to sort and store any solid and liquid waste on-site properly prior to disposal.Table 5.1 Tagged Coral Monitoring Locations, Time and Frequency
Monitoring Location |
Monitoring Month/Year |
Frequency |
No. of Monitoring Survey |
10 selected hard coral colonies at control site / indirect impact site |
1st Month |
Weekly Survey |
4 |
2nd to 3th Months |
Monthly Survey |
2 |
|
4th Month (postponed to 5th month due to diver accident in Shek Kwu Chau in October 2018) |
Re-tagging of Coral Colonies in Indirect Impact Site after Typhoon Mangkhut |
||
4th Month (postponed to 5th month due to diver accident in Shek Kwu Chau in October 2018 and further postpone to 6th month due to adverse weather) |
Re-tagging of Coral Colonies in Control Site after Typhoon Mangkhut |
||
5th Month (postponed to 6th month due to diver accident in Shek Kwu Chau and further postponed to 7th month due to delay of re-tagging activities at both Indirect Impact Site and Control Site) |
Post Re-tagging Monthly Survey |
1 |
|
7th to 76th Months (postponed to 8th to 76th month due to diver accident in Shek Kwu Chau in October 2018) |
Quarterly Survey |
23 |
|
16 translocated hard coral colonies and 10 selected natural hard coral colonies at recipient site R3 |
1st Year |
Quarterly Survey |
4 |
|
Figure 5.1 Tagged Natural Corals at Indirect Impact Site Near SKC for re-tagging after typhoon Mangkhut |
|
Figure 5.2 Tagged Natural Corals at Control Site Near Yuen Kong Chau for baseline |
|
Figure 5.3 Tagged Translocation Corals at Recipient Site R3 near SKC |
Table 5.2 Tagged Natural Corals during Baseline at Control Site near Yuen Long Chau
Coral # |
GPS Coordinates |
|
1 |
N22°0945.96 |
E113°5457.81 |
2 |
N22°0945.88 |
E113°5457.89 |
3 |
N22°0945.81 |
E113°5457.78 |
4 |
N22°0945.70 |
E113°5457.95 |
5 |
N22°0945.83 |
E113°5457.81 |
6 |
N22°0945.75 |
E113°5458.02 |
7 |
N22°0945.65 |
E113°5457.94 |
8 |
N22°0945.53 |
E113°5457.90 |
9 |
N22°0946.23 |
E113°5454.70 |
10 |
N22°0946.40 |
E113°5457.79 |
Table 5.3 Tagged Natural Corals during Baseline at Indirect Impact Site near SKC
Coral # |
GPS Coordinates |
|
11 |
N22°1129.12 |
E113°5908.98 |
12 |
N22°1129.08 |
E113°5909.06 |
13 |
N22°1129.01 |
E113°5909.21 |
14 |
N22°1129.01 |
E113°5909.29 |
15 |
N22°1129.00 |
E113°5909.37 |
16 |
N22°1129.00 |
E113°5909.50 |
17 |
N22°1128.94 |
E113°5909.48 |
18 |
N22°1128.99 |
E113°5909.36 |
19 |
N22°1128.95 |
E113°5909.29 |
20 |
N22°1129.00 |
E113°5909.18 |
Table 5.4 Re-tagged Natural Corals after Typhoon Manghkut at Indirect Impact Site near SKC
Coral # |
GPS Coordinates |
|
11 |
N22°1129.14 |
E113°5908.92 |
12 |
N22°1129.12 |
E113°5909.01 |
13 |
N22°1129.11 |
E113°5909.07 |
14 |
N22°1129.13 |
E113°5909.12 |
15 |
N22°1129.10 |
E113°5909.18 |
16 |
N22°1129.07 |
E113°5909.23 |
17 |
N22°1129.17 |
E113°5908.86 |
18 |
N22°1129.14 |
E113°5908.94 |
19 |
N22°1129.20 |
E113°5908.81 |
20 |
N22°1129.18 |
E113°5908.91 |
· Hard coral: Percentage of surface area exhibiting partial mortality and blanched/bleached area of each coral colony and degree of sedimentation.
5.5 Action and Limit Levels 5.5.1 Monitoring result was reviewed and compared against the below Action Level and Limit Level (AL/LL) as set with the below Table 5.5 and Table 5.6.Table 5.5 Action and Limit Levels for Construction Phase Coral Monitoring
Parameter |
Action Level |
Limit Level |
Mortality |
If during Impact Monitoring a 15% increase in the percentage of partial mortality on the corals occurs at more than 20% of the tagged indirect impact site coral colonies that is not recorded on the tagged corals at the control site, then the Action Level is exceeded. |
If during Impact Monitoring a 25% increase in the percentage of partial mortality on the corals occurs at more than 20% of the tagged indirect impact site coral colonies that is not recorded on the tagged corals at the control site, then the Limit Level is exceeded. |
Table 5.6 Action and Limit Levels for Post-Translocation Coral Monitoring
Parameter |
Action Level |
Limit Level |
Mortality |
If during Post-Translocation Monitoring a 15% increase in the percentage of partial mortality on the corals occurs at more than 20% of the translocated coral colonies that is not recorded on the original corals in the recipient site, then the Action Level is exceeded. |
If during Post-Translocation Monitoring a 25% increase in the percentage of partial mortality on the corals occurs at more than 20% of the translocated coral colonies that is not recorded on the original corals in the recipient site, then the Limit Level is exceeded. |
Table 5.7 Weather Condition for the Re-tagging Coral Colonies at Indirect Impact Site
Date |
Condition |
Average Underwater Visibility |
23 November 2018 |
- Southwest force 4 to 5 - Sunny period |
Less than 0.5m |
Table 5.8 Sizes, Condition, Mortality, Bleaching and Sediment of 10 Re-tagged Natural Coral Colonies at Indirect Impact Site
Tag # |
Species |
Size (cm) Max. Diameter |
Condition |
Mortality (%) |
Bleaching (%) |
Sediment (%) |
11 |
Cyphastrea serailia |
48 |
Good |
0 |
0 |
0 |
12 |
Favites chinensis |
27 |
Good |
0 |
0 |
0 |
13 |
Turbinaria peltata |
21 |
Good |
0 |
0 |
0 |
14 |
Favites chinensis |
8 |
Good |
0 |
0 |
0 |
15 |
Goniopora stutchburyi |
11 |
Good |
0 |
0 |
0 |
16 |
Psammocora superficialis |
27 |
Good |
0 |
0 |
0 |
17 |
Favites chinensis |
15 |
Good |
0 |
0 |
0 |
18 |
Psammocora superficialis |
39 |
Good |
0 |
0 |
0 |
19 |
Psammocora superficialis |
42 |
Good |
0 |
0 |
0 |
20 |
Psammocora superficialis |
29 |
Good |
0 |
0 |
0 |
Photo Plate 5.1 Re-tagged Corals at Indirect Impact Site
Tag # |
23 November 2018 |
#11 |
|
#12 |
|
#13 |
|
#14 |
|
#15 |
|
#16 |
|
#17 |
|
#18 |
|
#19 |
|
#20 |
|
5.6.3 Construction phase monitoring survey will be carried out to audit any effect to the health of tagged coral colonies during the whole construction period at both sites.
6. Marine Mammal 6.1 Monitoring Requirements 6.1.1 The marine mammal monitoring programme would focus on Finless Porpoise, as the study area near Shek Kwu Chau has been identified as a hotspot for this species, while the Chinese White Dolphins rarely occurred there in the past. 6.1.2 The monitoring would verify the predicted impacts on marine mammals, and examine whether the mitigation measures recommended in the EIA report have been effectively implemented to protect marine mammals from negative impacts from construction activities. 6.1.3 The Vessel-based Line-transect Survey, the Passive Acoustic Monitoring and the Land-based Theodolite Tracking will be conducted to provide systematic, quantitative measurements of occurrence, encounter rate, habitat use, movement and behavioural patterns of marine mammals within or near the Project Area during construction and operational phases. 6.1.4 The mammal monitoring works during construction consist of the following three survey methods:
· Vessel-based Line-transect Survey to monitor the occurrence of Finless Porpoises (and Chinese White Dolphins) in the study area during construction works, by comparing with the findings of the pre-construction marine mammal monitoring;
· Passive Acoustic Monitoring to study the usage of the Project Area and two control sites in South Lantau Waters by Finless Porpoise during construction works, in reference with the baseline findings of the pre-construction marine mammal monitoring; and
· Land-based Theodolite Tracking to study the movement and behavioral pattern of Finless Porpoise within and around the Project Area during construction works.
6.1.5 The marine mammal observation works of Marine Mammal Exclusion Zone (MMEZ) and Marine Mammal Watching as two of the specific mitigation measures recommended in the approved EIA report shall be fully and properly implemented for the Project to minimize disturbance on Finless Porpoise during construction and operational phases. 6.2 Survey Methods 6.2.1 Vessel-based Line-transect Survey For the vessel-based marine mammal surveys, the monitoring team adopted the standard line-transect method (Buckland et al. 2001) as same as that adopted during the EIA study and pre-construction phase monitoring to allow fair comparison of marine mammal monitoring results. Eight transect lines are set at Southeast Lantau survey area, including Shek Kwu Chau, waters between Shek Kwu Chau and the Soko Islands, inshore waters of Lantau Island (e.g. Pui O Wan) as well as southwest corner of Cheung Chau as shown in Figure 6.1 below:
|
Figure 6.1 Line Transects for Marine Mammal Surveys |
Table 6.1 Vessel-based Line-transect Survey Frequency
Season |
Months |
Frequency |
Peak Season |
December, January, February, March, April & May |
Twice per month |
Non-peak Season |
June, July, August, September, October & November |
Once per month |
SPSE = ((S / E) x 100) / SA%
DPSE = ((D / E) x 100) / SA%
where S = total number of on-effort sightings
D = total number of dolphins/porpoises from on-effort sightings
E = total number of units of survey effort
SA% = percentage of sea area
6.2.2 Passive Acoustic Monitoring (PAM) The PAM aims to study the usage of an area by Finless Porpoise by using an array of automated static porpoise detectors (e.g. C-POD) which would be deployed at different locations to detect the unique ultra-high frequency sounds produced by Finless Porpoise. During the construction period, the PAM survey will be conducted including placement of two passive porpoise detectors outside the Project Area as control site (i.e. within Pui O Wan and to the south of Tai A Chau) and one porpoise detector within the Project Area (i.e. near Shek Kwu Chau) as shown in Figure 6.2 below.
|
Table 6.2 PAM Deployment Period
Season |
Months |
Deployment Period |
Peak Season |
December, January, February, March, April or May |
At least 30 days during the peak months of porpoise occurrence in South Lantau waters |
|
Figure 6.3 Locations of Land-based Theodolite Tracking |
Table 6.3 Land-based Theodolite Tracking Survey Period
Season |
Months |
Survey Period |
Peak Season |
December, January, February, March, April or May |
30 days during the peak months of porpoise occurrence in South Lantau waters |
|
Figure 6.4 Illustration of Typical MMEZ |
Table 6.4 Summary of Vessel-based Line-transect Survey Effort
Date |
Area* |
Beaufort |
Effort (km) |
Season |
Vessel |
Effort Type** |
6-Nov-2018 |
SEL |
1 |
4.9 |
AUTUMN |
SMRUHK |
P |
6-Nov-2018 |
SEL |
2 |
11.3 |
AUTUMN |
SMRUHK |
P |
6-Nov-2018 |
SEL |
3 |
14.1 |
AUTUMN |
SMRUHK |
P |
6-Nov-2018 |
SEL |
4 |
9.2 |
AUTUMN |
SMRUHK |
P |
* As shown in Figure. 6.1
** P (from AFCD) denotes the ON EFFORT survey on the transect line, not the adjoining passages
Table 6.5 Sightings recorded during November 2018 Vessel-based Line-transect Survey
Figure 6.5 Location of sightings recorded during November 2018 Vessel-based Line-transect Survey
Date |
Species |
Sighting No. |
Time |
Group Size |
PSD |
Behaviour |
Latitude |
Longitude |
Area |
Effort Type |
Season |
6-Nov-2018 |
Finless Porpoise |
1 |
11:47 |
1 |
139 |
Unknown |
22.18955 |
113.9735 |
SEL |
Impact |
AUTUMN |
1. Agriculture, Fisheries and Conservation Department (AFCD) 2018. Annual Marine Mammal Monitoring Programme April 2017-March 2018) The Agriculture, Fisheries and Conservation Department, Government of the Hong Kong SAR.
http://www.afcd.gov.hk/english/conservation/con_mar/con_mar_chi/con_mar_chi_chi/con_mar_chi_chi.html
2. Agriculture, Fisheries and Conservation Department (AFCD) 2017. Annual Marine Mammal Monitoring Programme April 2016-March 2017) The Agriculture, Fisheries and Conservation Department, Government of the Hong Kong SAR.
http://www.afcd.gov.hk/english/conservation/con_mar/con_mar_chi/con_mar_chi_chi/con_mar_chi_chi.html
3. Agriculture, Fisheries and Conservation Department (AFCD) 2016. Annual Marine Mammal Monitoring Programme April 2015-March 2016) The Agriculture, Fisheries and Conservation Department, Government of the Hong Kong SAR.
http://www.afcd.gov.hk/english/conservation/con_mar/con_mar_chi/con_mar_chi_chi/con_mar_chi_chi.html
4. Agriculture, Fisheries and Conservation Department (AFCD) 2015. Annual Marine Mammal Monitoring Programme April 2014-March 2015) The Agriculture, Fisheries and Conservation Department, Government of the Hong Kong SAR.
http://www.afcd.gov.hk/english/conservation/con_mar/con_mar_chi/con_mar_chi_chi/con_mar_chi_chi.html
5. Agriculture, Fisheries and Conservation Department (AFCD) 2014. Annual Marine Mammal Monitoring Programme April 2013-March 2014) The Agriculture, Fisheries and Conservation Department, Government of the Hong Kong SAR.
http://www.afcd.gov.hk/english/conservation/con_mar/con_mar_chi/con_mar_chi_chi/con_mar_chi_chi.html
6. Agriculture, Fisheries and Conservation Department (AFCD) 2013. Annual Marine Mammal Monitoring Programme April 2012-March 2013) The Agriculture, Fisheries and Conservation Department, Government of the Hong Kong SAR.
http://www.afcd.gov.hk/english/conservation/con_mar/con_mar_chi/con_mar_chi_chi/con_mar_chi_chi.html
7. Agriculture, Fisheries and Conservation Department (AFCD) 2012. Annual Marine Mammal Monitoring Programme April 2011-March 2012) The Agriculture, Fisheries and Conservation Department, Government of the Hong Kong SAR.
http://www.afcd.gov.hk/english/conservation/con_mar/con_mar_chi/con_mar_chi_chi/con_mar_chi_chi.html
8. Agriculture, Fisheries and Conservation Department (AFCD) 2011. Annual Marine Mammal Monitoring Programme April 2010-March 2011) The Agriculture, Fisheries and Conservation Department, Government of the Hong Kong SAR.
http://www.afcd.gov.hk/english/conservation/con_mar/con_mar_chi/con_mar_chi_chi/con_mar_chi_chi.html
9. Agriculture, Fisheries and Conservation Department (AFCD) 2010. Annual Marine Mammal Monitoring Programme April 2009-March 2010) The Agriculture, Fisheries and Conservation Department, Government of the Hong Kong SAR.
http://www.afcd.gov.hk/english/conservation/con_mar/con_mar_chi/con_mar_chi_chi/con_mar_chi_chi.html
Table 7.1 List of Equipment Used during Construction Phase Monitoring
Equipment |
Quantity |
Swarovski EL 8.5 x 42 Binocular |
1 |
Swarovski EL Range 8 x 42 Binocular |
1 |
Swarovski ATX 25-60 x 85 Spotting Scope |
1 |
Canon 1Dx Mark II Camera |
1 |
Canon EF300mm F2.8 Lens with Canon 2x Teleconverter |
1 |
Canon PowerShot G7X Camera |
1 |
Garmin GPSMAP 64S |
1 |
Table 7.2 Weather Conditions during the WBSE Monitoring
Date |
Condition |
Temperature (℃) |
23 November 2018 |
- Southeast 4 to 5 - Sunny periods |
27 |
|
Figure 7.1 Location of WBSE Nest on SKC |
|
Figure 7.2 Photo Record of WBSE on SKC During the Reporting Period |
Figure 8.1 Environmental Complaint Handling Procedure
Table 8.1 Summary of SS Compliance Status at Impact Stations (Mid-Ebb Tide)
Date |
B1 |
B2 |
B3 |
B4 |
CR1 |
CR2 |
F1 |
H1 |
S1 |
S2 |
S3 |
M1 |
1-11-2018 |
Cancelled due to Typhoon YUTU |
|
|
|
|
Cancelled due to Typhoon YUTU |
||||||
3-11-2018 |
|
|
|
|
|
|
|
|
|
|
|
|
5-11-2018 |
|
|
|
|
|
|
|
|
|
|
|
|
7-11-2018 |
|
|
|
|
|
|
|
|
|
|
|
|
9-11-2018 |
|
|
|
|
|
|
|
|
|
|
|
|
13-11-2018 |
|
|
|
|
|
|
|
|
|
|
|
|
15-11-2018 |
|
|
|
|
|
|
|
|
|
|
|
|
17-11-2018 |
|
|
|
|
|
|
|
|
|
|
|
|
19-11-2018 |
|
|
|
|
|
|
|
|
|
|
|
|
21-11-2018 |
|
|
|
|
|
|
|
|
|
|
|
|
23-11-2018 |
|
|
|
|
|
|
|
|
|
|
|
|
26-11-2018 |
|
|
|
|
|
|
|
|
|
|
|
|
28-11-2018 |
|
|
|
|
|
|
|
|
|
|
|
|
30-11-2018 |
|
|
|
|
|
|
|
|
|
|
|
|
No. of SS Exceedances |
2 |
4 |
2 |
5 |
2 |
4 |
4 |
5 |
0 |
0 |
0 |
2 |
Note 1: Detailed results are presented in Appendix D
Legend:
|
No exceedance of Action Level and Limit Level |
|
Exceedance of Action Level recorded at monitoring station located downstream of the Project based on dominant tidal flow |
|
Exceedance of Action Level recorded at monitoring station located upstream/unrelated stream (neither upstream nor downstream, far away) of the Project based on dominant tidal flow |
|
Exceedance of Limit Level recorded at monitoring station located downstream of the Project based on dominant tidal flow |
|
Exceedance of Limit Level recorded at monitoring station located upstream/unrelated stream of the Project based on dominant tidal flow |
|
Upstream/unrelated stream station with respect to IWMF Project during the respective tide based on dominant tidal flow |
|
Downstream station with respect to IWMF Project during the respective tide based on dominant tidal flow/station within the Project site |
|
NA for measurement |
|
Cancelled due to incident or adverse weather |
Table 8.2 Summary of SS Compliance Status at Impact Stations (Mid-Flood Tide)
Date |
B1 |
B2 |
B3 |
B4 |
CR1 |
CR2 |
F1 |
H1 |
S1 |
S2 |
S3 |
M1 |
1-11-2018 |
Cancelled due to Typhoon YUTU |
|||||||||||
3-11-2018 |
|
|
|
|
|
|
|
|
|
|
|
|
5-11-2018 |
|
|
|
|
|
|
|
|
|
|
|
|
7-11-2018 |
|
|
|
|
|
|
|
|
|
|
|
|
9-11-2018 |
|
|
|
|
|
|
|
|
|
|
|
|
13-11-2018 |
|
|
|
|
|
|
|
|
|
|
|
|
15-11-2018 |
|
|
|
|
|
|
|
|
|
|
|
|
17-11-2018 |
|
|
|
|
|
|
|
|
|
|
|
|
19-11-2018 |
|
|
|
|
|
|
|
|
|
|
|
|
21-11-2018 |
|
|
|
|
|
|
|
|
|
|
|
|
23-11-2018 |
|
|
|
|
|
|
|
|
|
|
|
|
26-11-2018 |
|
|
|
|
|
|
|
|
|
|
|
|
28-11-2018 |
|
|
|
|
|
|
|
|
|
|
|
|
30-11-2018 |
|
|
|
|
|
|
|
|
|
|
|
|
No. of SS Exceedances |
3 |
4 |
2 |
0 |
1 |
4 |
1 |
0 |
0 |
0 |
0 |
3 |
Note 1: Detailed results are presented in Appendix D
Legend:
|
No exceedance of Action Level and Limit Level |
|
Exceedance of Action Level recorded at monitoring station located downstream of the Project based on dominant tidal flow |
|
Exceedance of Action Level recorded at monitoring station located upstream/unrelated stream (neither upstream nor downstream, far away) of the Project based on dominant tidal flow |
|
Exceedance of Limit Level recorded at monitoring station located downstream of the Project based on dominant tidal flow |
|
Exceedance of Limit Level recorded at monitoring station located upstream/unrelated stream of the Project based on dominant tidal flow |
|
Upstream/unrelated stream station with respect to IWMF Project during the respective tide based on dominant tidal flow |
|
Downstream station with respect to IWMF Project during the respective tide based on dominant tidal flow/station within the Project site |
|
NA for measurement |
|
Cancelled due to adverse weather |
9. EM&A Site Inspection 9.1 Site inspections were carried out on a weekly basis to monitor the implementation of proper environmental pollution control and mitigation measures under the Contract. In the reporting period, site inspections were carried out on 6, 13, 20 and 27 November 2018 at the site portions list in Table 9.1 below.
Table 9.1 Site Inspection Record
Date |
Inspected Site Portion |
Time |
6 November 2018 |
Portion 1, 1A & 1B (near SKC) |
10:30-11:40 |
13 November 2018 |
Portion 1, 1A & 1B (near SKC) |
10:20-11:40 |
20 November 2018 |
Portion 1, 1A & 1B (near SKC) |
10:40-11:40 |
27 November 2018 |
Portion 1, 1A & 1B (near SKC) |
10:30-11:25 |
Table 9.2 Site Observations
Date |
Environmental Observations |
Follow-up Status |
6 November 2018 (Site inspection) |
Observation(s) and Recommendation(s) 1. On FTB 16, no major observation was observed. 2. On Eun Sung 750, no major observation was observed. |
NA |
13 November 2018 (Site inspection) |
Observation(s) and Recommendation(s) Reminder: 1. Disposal record should be provided of sediment collected from 2. General refuse should be disposed of 3. On FTB 16, housekeeping should be maintained. |
NA |
20 November 2018 (Site inspection) |
Observation(s) and Recommendation(s) Reminder: 1. Before receiving the approved water discharge license, please be reminded not to discharge any treated or untreated sewage waste. 2. On FTB 20, please be reminded that paint cans in use should be put on drip tray. 3. On FTB 22, sand was used as absorbent for absorbing oily water on drip tray. Please be reminded that sand absorbed oily water should be treated as chemical waste. |
NA |
27 November 2018 (Site inspection) |
Observation(s) and Recommendation(s) 1. Undefined container and unlabelled bottles were found in chemical waste storage cabinet. 2. On FTB 16, oily water was observed near a drip tray. Reminders: 1. On FTB 16, housekeeping should be maintained. Reminded by SO: 1. Chemical waste should be collected and disposed of in middle of December, 2018. 2. Sewage from chemical toilet should be collected weekly. |
1. The chemical waste label had been displayed on chemical waste container. 2. The oily water was removed as chemical waste by absorbent pad and the absorbent pad was then stored in the chemical waste storage area. |
10. Future Key Issues 10.1 Works to be undertaken in the next reporting month are:
· Marine Site Investigation Works
· Coring of DCM samples conducted at site trial location
· Coring of DCM samples conducted at DCM Static Lading Test sites
· Coring for Instrumentation at DCM Static Lading Test sites
· Laying of Geotextile and Sand Blanket for DCM Injection Works
· DCM Injection Works
10.2 Potential environmental impacts arising from the above construction activities are mainly associated with water quality, construction noise, waste management and ecology. 10.3 The key environmental mitigation measures for the Project in the coming reporting period expected to be associated with the construction activities include:· Reduction of noise from equipment and machinery on-site;
· Installation of silt curtains for the sand blanket laying works;
· Sorting, recycling, storage and disposal of general refuse and construction waste;
· Management of chemicals and avoidance of oil spillage on-site, especially under heavy rains and adverse weather; and
· Implementation of MMEZ and inspection of enclosed environment within silt curtains as per DMPFP
10.4 The tentative schedule of regular construction noise, water quality and ecology monitoring in the next reporting period is presented in Appendix P. The regular construction noise, water quality and ecology monitoring will be conducted at the same monitoring locations in the next reporting period.11. Conclusion and Recommendations 11.1 This 5th monthly Environmental Monitoring and Audit (EM&A) Report presents the EM&A works undertaken during the period from 1 November 2018 to 30 November 2018, in accordance with the Updated EM&A Manual and the requirement under EP- 429/2012/A and FEP-01/429/2012/A. 11.2 Construction noise, water quality, construction waste, marine mammal and WBSE monitoring were carried out in the reporting period. No project-related exceedance of the Action and Limit Level was recorded during the reporting period, however, environmental deficiencies of the Contractor on the implementation of silt curtain deployment system were spotted. 11.3 The Contractor has been reminded to facilitate the ETs investigation by promptly providing site records and information. 11.4 Weekly environmental site inspection was conducted during the reporting period. Environmental deficiencies were observed during site inspection and were rectified. 11.5 According to the environmental site inspections performed in the reporting month, the Contractor is reminded to pay attention on maintaining site tidiness and avoidance of oil spillage on-site, especially under heavy rains and adverse weather. 11.6 Regarding to the deployment of silt curtains as a principal water quality impact mitigation measures on various marine works, the Contractor has been reminded to follow strictly to the design and checking procedure as specified in the Silt Curtain Deployment Plan. The Contractor is reminded that all measures recommended in the deposited silt curtain deployment plan shall be fully and properly implemented for the Project as per EP condition 2.6 of the FEP. 11.7 Diver checking by the Contractor was resumed in the reporting period after the diver accident in October to conduct inspection on the status of silt curtain underwater. 11.8 No environmental complaint was received in the reporting period. 11.9 No notification of summons or prosecution was received since commencement of the Contract. 11.10 The ET will keep track on the construction works to confirm compliance of environmental requirements and the proper implementation of all necessary mitigation measures.